Report from Charter Construction
Freedom — July 28, 2020 — Crest gate #1 of 2 was set last week, which is another major milestone for the new Ossipee Lake Dam. Gate #2 is scheduled to be set in early August.
Moore Crane Service of Dover, NH, handled the rigging and heavy lifting of the 40′ x 6.5′, 14-ton gate fabricated by Steel-Fab of Fitchburg, MA.
Our field construction crew is led by Steve Laroche, with Nick D’Ambruoso, Brian Granger, Dave Osterhoudt, Dean Robertson and Ron Flamont.